Post by: lacoste on October 25, 2009, 08:39:14 pm
Dont understand crashing activity B will create a new critical path, why does the assessors report say it doesnt?

Title: Re: Q9 VCAA Networks EXAM ONE
Post by: plato on October 25, 2009, 11:32:24 pm
Dont understand crashing activity B will create a new critical path, why does the assessors report say it doesnt?



If this refers to the 2008 paper, I don't understand your question. There is no reference to crashing activity B in 2008.
Title: Re: Q9 VCAA Networks EXAM ONE
Post by: kazoospasm on October 25, 2009, 11:46:41 pm
Maybe they mean option B? If so, I don't see the mistake.

The original critical path, ACFHJL, has a completion time of 22 days. The only path using G (ACGKL) takes 20 days. Increasing G by 1 day makes it 21 days, so it's not a critical path.

Increasing activity D by 7 makes ABDJL go from 15 to 22 days.
Title: Re: Q9 VCAA Networks EXAM ONE
Post by: lacoste on October 26, 2009, 09:12:19 am
Sorry meant for the 2006 paper.

:)
Title: Re: Q9 VCAA Networks EXAM ONE
Post by: lacoste on October 26, 2009, 03:38:45 pm
Thanks figured it out :):)