Author Topic: Crashing Help?  (Read 632 times)  Share 

0 Members and 1 Guest are viewing this topic.

johnsmith123

  • Victorian
  • Trailblazer
  • *
  • Posts: 38
  • Respect: 0
Crashing Help?
« on: May 08, 2013, 05:20:27 pm »
0
hi

I need help with Questions 4 and 5, I have my answer but it is different to the suggested solutions, so please tell me what you get becuase I think my answer is correct. Thanks

plato

  • Victorian
  • Forum Obsessive
  • ***
  • Posts: 317
  • Respect: +11
Re: Crashing Help?
« Reply #1 on: May 11, 2013, 11:07:07 pm »
0
My answers are:
4(a) Activity E starts at the end of B and joins to the end of C. Then activity F starts at the ends of C&E and joins at the end of Activity D
4(b) LST for C is 6. EST for F is 12.
4(c)  ABEFG
4(d) 15

5(a) Crash B by 3 and E by 1 which reduces ABEFG to 11. But this makes a new critical path ACFG of length 12. So then crash C by 1 to give the shortest possible time along two critical paths of ABEFG and ACFG, both 11 long.
5(b) 3 week saving costs $12000 by crashing E by 1 and B by 2.
       4 week saving costs $21000 by crashing E by 1, B by 3 and C by 1 as explained in answer to 5(a)
« Last Edit: May 12, 2013, 12:07:13 am by plato »