« on: September 24, 2010, 12:11:40 am »
0
Hi guys,

i need help with these questions

b) LST for C, i got 27 where as the answer is 26

e) the completion time i got is 38 days where as the answer is 37 days

what am i doing wrong? and why is a day longer than what i had? :S  :( >:( :o >:( ;D :D :D :D :D :D :D

cheers! help appreciated
« Last Edit: September 24, 2010, 11:41:47 am by nbalakers24 »

_avO

  • Victorian
  • Part of the furniture
  • *****
  • Posts: 1915
  • Respect: +15
Re: Networks - help
« Reply #1 on: September 24, 2010, 08:54:58 am »
0
Can you show the original network or the duration of each activity, there's insufficient data there to determine the float/LST
2011-2014: Bachelor of Commerce/Economics @ Monash Clayton

nbalakers24

  • Victorian
  • Forum Leader
  • ****
  • Posts: 672
  • Respect: +2
Re: Networks - help
« Reply #2 on: September 24, 2010, 11:41:25 am »
0
whoops forgot the precedence table LOL upped

_avO

  • Victorian
  • Part of the furniture
  • *****
  • Posts: 1915
  • Respect: +15
Re: Networks - help
« Reply #3 on: September 24, 2010, 11:55:20 am »
0
Yeah from the table, you have the correct answers, 38 days completion time and LST of C is 27.. They must have done something wrong
2011-2014: Bachelor of Commerce/Economics @ Monash Clayton

nbalakers24

  • Victorian
  • Forum Leader
  • ****
  • Posts: 672
  • Respect: +2
Re: Networks - help
« Reply #4 on: September 24, 2010, 12:26:09 pm »
0
sweet thanks! :D