Yea but the lead time should be 7 days because:
Task A takes 5 days
in which task B will start at the same time taking only 2 days.
BUT, you have to wait an extra two days after task A is complete, therefore Task C can only start 7 Days after the project begins? Therefore lead time = 7 days?
Slack time = 3, sorry typo.
Task C has a lag time of 2 days? as it must wait those 2 days extra days?
Umm and assuming task a and b start at the same time,
I think
Task C has 5 days lead time (By definition)
Task B has 3 days slack time (Task B can run over 3 days, meaning it finishes at the same time as Task A, thus not effecting the deadline)
Task B also has 3 days lag time (If the project runs accordingly, Task C begins immediately after Task A (because longest task), and Task A is 3 days longer then Task B, meaning the lag time is also 3 days)
Therefore, Slack Time = Lag Time?
Remember, lag time is the amount of time a task can run over time without affecting the critical path. Task B can run over time, not Task C
Thats my understanding of it, but I may be wrong.
No, task C must wait an extra 2 days as specified. So would the lag time become 7 days?
Edit: this is literally the worst thing that could happen 16 hours before an exam..