http://www.vcaa.vic.edu.au/vce/studies/mathematics/further/pastexams/2007/2007furmath2.pdf

Can someone explain the logic behind the answer of question 4d in networks. I got 16 weeks, but the assessors report says 15 weeks.

plato

  • Victorian
  • Forum Obsessive
  • ***
  • Posts: 317
  • Respect: +11
Re: 2007 Networks
« Reply #1 on: November 06, 2011, 09:01:23 pm »
0
If you cut F and C by 2 weeks each, you will get a new critical path through E
Then you can cut E by one week to further shorten the project.
There are now two new critical paths: BEHI or BCFHI and each are 15 weeks long

smithy16

  • Victorian
  • Trendsetter
  • **
  • Posts: 122
  • Respect: +5
Re: 2007 Networks
« Reply #2 on: November 06, 2011, 09:05:25 pm »
0
Ahhh, so basically it is asking you to try to make the shortest critical path, by removing two weeks off A,C,E,F and G. And you only take 1 of E because taking any more of won't affect the critical path. Thank you :)