Project crashing
« on: September 09, 2016, 07:05:50 am »
0
Project crashing - could somebody please explain to me when you know you can't crash a project any further? Many have said 'when it's no longer cost effective'...so how do you know when it's no longer cost effective? Thank you...
Tutoring Global Politics (44) and Legal Studies (47). PM for information.

ATAR 2016: 97.00

Monash Law(Hons)/Arts, 80+ WAM.

FurtherStar

  • Adventurer
  • *
  • Posts: 7
  • That's dedication right there ^^
  • Respect: 0
Re: Project crashing
« Reply #1 on: September 09, 2016, 01:17:55 pm »
+3
Project crashing - could somebody please explain to me when you know you can't crash a project any further? Many have said 'when it's no longer cost effective'...so how do you know when it's no longer cost effective? Thank you...

Hey Emily,

As I understand it, an activity may be crashed by however many hours (for example), so long as this doesn't create a new critical path.

For example:

Assume that path B-D-E-F of a project is critical, taking a maximum of 26 hours. Let's also assume that activity B has a duration of 5 hours.

Let our next path (which is second closest to being critical) be A-D-G-F, which takes 24 hours.

Therefore we can only crash activity B by 2 hours, so that our current critical path (B-D-E-F) is equal to the maximum time of our second path (A-D-G-F). If we were to crash B by 3 hours, A-D-G-F would be our new critical path (24) as it would take longer than our initial, which would now be (23).

Sorry for the long explanation. I hope I answered your question.